WPM has the personnel and experience to manage the installation of minor facilities and pipeline projects if the client requires. Some of the projects that WPM personnel have managed include:
Purchase and installed of a sour oil and gas facility with a horizontal free-water knockout to process high water cut volumes of 2,000 m3 of fluid per day and 4 MMCF of gas per day.
Evaluated, repaired, licensed and re-commissioned a 6” abandon sweet gas line to transport 5% H2S gas.
Designed, licensed and installed single well battery and 5 KM of 88.9mm pipeline to handle 100 m3 fluid and 2 MMCF per day that contained 4% H2S.
Installed 2 to 5 km sweet gas pipelines in central Alberta.
Design and installation of sweet gas compressor facilities.